ANNUAL FISCAL, PERFORMANCE, AND COMPLIANCE AUDITS

PROJECT TIMETABLE
December 19, 2018.....................Issue Request for Proposals
February 8, 2019, 4:00 PM....... Closing Date for Receipt of Proposals
February 11, 2019........................Finalists contacted to schedule
interviews, if required
February 15, 2019........................Conduct interviews, if required
March 7, 2019.............................. Contract award
End of August.............................. Audit fieldwork begins
End of October............................ Draft Financial Statements
Mid November............................. Final Financial Statements

Proposals must be received no later than 4:00 pm on February 8, 2019 at the EDCTC office.