City of Placerville Highway 50 Operational Improvements Project Update

UPCOMING ROADWAY WORK INVOLVING ROADWAY CLOSURE
May, 2008

56% work completed, 69% time elapsed

Work completed during April 2008
• West Placerville Drive UC foundations/walls at west abutment, excavate east abutment
• Moved monument at Bedford and Main (DA’s office)
• Curb and gutter at Bedford and Main and near retaining walls at Canal
• Restriped extra lane on Main Street approach to Spring Street bridge
• Bedford POC – north side retaining wall work, precast cap on south side columns
• Diversions installed in Hangtown Creek at Bedford, Spring, and Canal
• Excavation for east half of Bedford and east half Canal started
• PG&E working since 4/7/08, delay to Mitchell’s Curb & Gutter started 3/26/08
• Placerville Drive Connector AC paving from Pville Drive onramp to Forni Road – quality issues resulted in rejection
• Auxiliary lane subgrade excavated and aggregate base placed
• Pedestrian railing placed along Hangtown Creek Bridge

Work to take place over the next couple months
• Meet with AT&T to verify measures to protect cable across Bedford Bridge
• Keep pushing PG&E to finish Lower Main
• Parking areas along South side of lower Main Street – May 2008
• Parking areas along North side of lower Main Street – May 2008
• Bicycle side railing Hangtown Creek Bridge
• Replace AC on Placerville Drive connector to open Forni Road to US 50 East onramp
• Third segment westbound Highway 50 bridge at Placerville Drive UC
• Continue Hwy 50 signal and controller cabinet pads at Canal, Spring, and Bedford
• Sewer abandonment work in Hangtown Creek – starting in May 2008
• Complete east half each of Bedford, Canal, and Spring Street widenings

Project Contacts
Mic Restaino, Resident Engineer
Caltrans, 530-344-1691

Clark Peri, Project Manager
Caltrans, 916-274-0538

Randy Pesses, Director of Public Works
City of Placerville, 530-642-5250

Rick Tippett, City Engineer
City of Placerville, 530-642-5250



 

 

 

ROADWAY
The El Dorado County Transportation Commission (EDCTC) and its partner agencies have many current roadway and highway projects in process, from early planning stages to construction. These projects include:

For detailed information on EDCTC projects, see the Project Monitoring Reports below.

PROJECT MONITORING QUARTERLY REPORT

What is the EDCTC Project Monitoring Report?
EDCTC staff develops Project Monitoring Reports for transportation projects that are regionally significant or funded through the Commission by state and federal fund sources. The reports help to increase awareness of regional transportation issues and potential project delivery challenges.

EDCTC's Senior Transportation Planners develop the quarterly project monitoring reports. The local Report focuses on projects located in and around the City of Placerville, and the County-wide report focuses on projects located in the unincorporated areas of western El Dorado County.

Reports can be downloaded below in PDF format. If you have any questions, feel free to contact Jerry Barton 530-642-5267.

PROJECT MONITORING REPORT
March, 2008 black and white (530 kb)
March, 2008 color (1,195 kb)

 

get acrobat reader