City of Placerville Highway 50 Operational Improvements Project Update
As of December 4, 2008
Report from Mic Restaino, Caltrans Resident Engineer
Improvements 82% work, 82% time
Bid
Opening Date: February 8, 2006
Bid
Approved on May 8, 2006
Low
bidder Mitchell Engineering $34,154,559.40
-
Location 1 – Connect West Placerville Drive with Main Street and Forni
Road; includes construction of new Hangtown Creek Bridge and replacement
(three stages) of the Highway 50/West Placerville Drive Undercrossing
-
Location 2 – Widen eastbound Highway 50, replace the Bedford Avenue
Pedestrian overcrossing and improve the operation of local cross traffic
by widening three bridges that connect Main Street to Highway 50 (Bedford,
Spring, and Canal Street)
-
Relocation of the City of Placerville sewer line, approximately half is
new mainline and half is collector replacement
-
Construction anticipated to be complete second quarter calendar year 2009
Work completed during November 2008
-
Hangtown Creek realignment – planted willows
-
Cleanup and installed winterization measures – 3.8 acres still active
-
West Placerville Drive udercrossing offramp – final paving
-
West Placerville Drive undercrossing onramp – final paving
-
West Placerville Drive Connector – completed slope paving under U.S.
50 bridge
-
U.S. 50 – final lift and permanent striping on westbound from Canal
to west end of project
-
U.S. 50 – removed and replaced AC eastbound (45mm final lift remains)
-
Finished paving business parking area – lower Main Street (striping
remains)
-
Bedford, Spring, and Canal roadways – removed and replaced distressed
AC, temporary striping
-
Bedford, Spring, and Canal Bridges – installed ledgestone veneer for
barriers
-
Bedford, Spring, and Canal Bridges – installed polyester paving (except
east half of Bedford which is scheduled for next week)
-
Electrical services – PG&E meters installed, most decorative lights
are active
-
Installed metal railing on eastbound U.S. 50 barrier
-
Bedford Pedestrian Overcrossing (POC)– center column and northerly
anchor completed, falsework over U.S. 50 westbound span installed
Work to take place over the next few months
-
Plant special “liner plants” along bottom of Hangtown Creek
Realignment
-
West Placerville Drive Connector – complete striping and install signs
-
Bedford Roadway – remove and replace last distressed AC area, temporary
striping
-
Bedford Bridge – finish last half of polyester paving
-
Bedford POC – walls and ramps on north side of U.S. 50
-
Bedford POC – falsework for span over eastbound 50 on 12/15/08
-
Signs
-
Lighting
-
Finish loops and signals
-
Remove fill from Caltrans Resident Engineer office area
-
U.S. 50 – new signals at Canal, Spring, and Bedford
Project
Contacts
Mic Restaino
Caltrans Resident
Engineer
(530) 344-1691
Clark Peri
Caltrans Project Manager
(916) 274-0538
Randy Pesses
City of Placerville Director of Public Works
(530) 642-5250
Rick Tippett
City of Placerville Engineer
(530) 642-5250
US 50 IMPROVEMENTS THROUGH THE CITY OF PLACERVILLE
Project
Description
The project, currently under construction, will result in many improvements
to increase capacity and improve traffic circulation on and around U.S. 50
through Placerville including:
- A direct connection
between Placerville Drive and Main Street under U.S. 50 and over Hangtown
Creek
- An eastbound
auxilliary lane along U.S. 50 from the Placerville Drive onramp to Clay
Street
- Improved traffic
signal coordination
- Widening of
the bridges over Hangtown Creek at Canal Street, Spring Street, and Bedford
Avenue
- Reconstruction
of the pedestrian overcrossing at Bedford Avenue