City of Placerville Highway 50 Operational Improvements Project Update

As of December 4, 2008
Report from Mic Restaino, Caltrans Resident Engineer
Improvements 82% work, 82% time
Bid Opening Date: February 8, 2006
Bid Approved on May 8, 2006
Low bidder Mitchell Engineering $34,154,559.40

Work to take place over the next few months

Project Contacts
Mic Restaino
Caltrans
Resident Engineer
(530) 344-1691

Clark Peri
Caltrans Project Manager
(916) 274-0538

Randy Pesses
City of Placerville Director of Public Works
(530) 642-5250

Rick Tippett
City of Placerville Engineer
(530) 642-5250



 

 

 

US 50 IMPROVEMENTS THROUGH THE CITY OF PLACERVILLE

Project Description
The project, currently under construction, will result in many improvements to increase capacity and improve traffic circulation on and around U.S. 50 through Placerville including: